Waterline Replacement Update

Waterline Replacement Update #3

 

This is the update we received from Wilson Contracting Services:

 

“We are looking at having the Bores on Phase 1A (Cayuga/Pawnee) completed in the next 20 working days. Service line drops in and ready to test in an additional 10 working days. Residential connections & meter box sets completed in and additional 10 working days.

 

Phase 2 (Entrance back toward Driving Range) Complete Pipeline and pressure test Phase 2, Service drops in and ready to test in 20 working days. Residential connections & meter box sets completed in and additional 24 working days.

Cleanup and grass establishment to be executed as we progress through the residential connections.”